DTL
QUALITY — AS/NZS 4130

HDPE ITP — Inspection & Test Points

Shark Bay Bitterns · Field Piping Installation
DTL-PRJ0072-ITP-001
Rev A
H Hold — work stops until released W Witness — attend if electedR Record only Change the DTL column if needed; SBR sets its own SBR hold/witness points; sign each point as it clears.
No.ActivityAcceptance criteriaReferenceRecordDTLSBRSigned / date
1.0   Material receival & storage
1.1Delivery inspectionPipe/fittings free of transit damage, gouges >10% wall, UV degradation.AS/NZS 4130Receival log
1.2Certification checkCoC & AS/NZS 4130 compliance certificate present; batch/heat recorded.SOW MDRTraceability record
1.3StorageSupported, shaded, no point loads; UV protection if >12 months.Mfr guidance
2.0   Butt fusion jointing
2.1Machine set-upCorrect clamps/inserts; faces aligned; drag pressure recorded.AS/NZS 4130 App.Weld register
2.2Heater plate tempPlate temperature within approved range, verified each shift.TEM-0003Heater Plate Check
2.3Fusion parametersHeat-soak, fusion & cooling times/pressures to approved parameters.TEM-0003Weld register
2.4Bead inspectionTwin uniform beads, correct width, no mismatch >10% wall; cooled undisturbed.AS/NZS 4130Weld register
2.5Weld numberingEach joint numbered and located on the weld map.QMPWeld map
3.0   Installation
3.1Stringing & alignmentRoute, bend radius ≥ mfr minimum, no kinks; support.DrawingITP sign-off
3.2Road crossings / coverDepth, sleeve/casing and cover to drawing.DrawingITP sign-off
3.3Earth moundingProfile and compaction to drawing.DrawingITP sign-off
4.0   Connections
4.1Flanged / mechanical jointsAlignment, gasket, bolt torque to spec; connection recorded.Mfr specConnection record
4.2ARV, tie-ins, standpipes, scourFit, orientation, function to drawing.DrawingITP sign-off
5.0   Testing & handover
5.1Pressure / leak testTest pressure, hold time and acceptance to approved test procedure.AS/NZS 4130 / specTest certificate
5.2Weld map completeAll welds mapped and cross-referenced to the register.QMPWeld map
5.3Records & MDRAll ITP points signed, NCRs closed, MDR compiled.SOW MDRMDR
Hold points (H) stop the work until released. Witness points (W) let SBR attend; work may proceed if SBR elects not to. SBR completes the SBR column at the ITP review; all completed records form part of the Manufacturers Data Report.
PREPARED / ISSUED — DTL
ACCEPTED — SBR
Saved