H Hold — work stops until releasedW Witness — attend if electedR Record onlyChange the DTL column if needed; SBR sets its own SBR hold/witness points; sign each point as it clears.
No.
Activity
Acceptance criteria
Reference
Record
DTL
SBR
Signed / date
1.0 Material receival & storage
1.1
Delivery inspection
Pipe/fittings free of transit damage, gouges >10% wall, UV degradation.
Route, bend radius ≥ mfr minimum, no kinks; support.
Drawing
ITP sign-off
3.2
Road crossings / cover
Depth, sleeve/casing and cover to drawing.
Drawing
ITP sign-off
3.3
Earth mounding
Profile and compaction to drawing.
Drawing
ITP sign-off
4.0 Connections
4.1
Flanged / mechanical joints
Alignment, gasket, bolt torque to spec; connection recorded.
Mfr spec
Connection record
4.2
ARV, tie-ins, standpipes, scour
Fit, orientation, function to drawing.
Drawing
ITP sign-off
5.0 Testing & handover
5.1
Pressure / leak test
Test pressure, hold time and acceptance to approved test procedure.
AS/NZS 4130 / spec
Test certificate
5.2
Weld map complete
All welds mapped and cross-referenced to the register.
QMP
Weld map
5.3
Records & MDR
All ITP points signed, NCRs closed, MDR compiled.
SOW MDR
MDR
Hold points (H) stop the work until released. Witness points (W) let SBR attend;
work may proceed if SBR elects not to. SBR completes the SBR column at the ITP review; all completed
records form part of the Manufacturers Data Report.